Rebar Cut Length Calculator

Cut length and bar weight with standard hook allowances.

Inputs

mm
mm
mm
pcs

Result

Formula

Clear lengthL = member length − 2 × cover
Hook allowancek × d (6.25 at 180°, 4.9 at 135°, 3.5 at 90°)
Cut lengthL_cut = L + 2 × allowance
Weight per barW = 0.00617 × d² × L_cut ÷ 1000 kg
A 6000 mm bar with 25 mm cover and 180° hooks at 20 mm: 5950 mm clear plus 125 mm per end gives a 6200 mm cut, 15.30 kg per bar and 1530 kg for 100 bars.

FAQ

Why is cut length not the drawing dimension?
Drawings give external dimensions measured to the outside face, but bending stretches the outside and compresses the inside — the centreline length is what you must cut. So sum the external segments and deduct a bend allowance at each bend, adding hook allowances at the ends. Getting this wrong scraps the whole batch.
Why is a 180° hook 6.25d?
The developed length is the half-circle (π × 2.5d ÷ 2 ≈ 3.93d) plus the straight tail, adjusted for bend elongation — 6.25d is the field value. Code editions differ slightly (some give 6.25d, others compute from a 2.5d bend diameter), so follow the standard your project cites.
How is a stirrup cut length calculated?
Stirrups use the external perimeter plus hook allowances, not 2 × 6.25d. Seismic stirrups have 135° hooks at 11.9d each, covering a 10d tail and the bend increment: length = 2(b − 2c) + 2(h − 2c) + 2 × 11.9d. There is a dedicated stirrup calculator on this site.