Masonry Mortar Mix Calculator

Cement, sand and water for M5-M15 mortar by volume, with a batch sheet.

Inputs

m³
%

Result

Formula

CementM = reference by grade × volume
42.5 classreference × 0.88
SandV = 1.02 × mortar volume (loose)
Water to addW = 280 × V − moisture in sand
Strength70.7 mm cube at 28 days
1 m³ of M7.5 with 32.5 class cement and 2% sand moisture: 220 kg cement (5 bags), 1.02 m³ of dry sand around 1479 kg and about 250 kg of added water — a ratio near 1 : 6.7.

FAQ

What does M7.5 mean?
A mean compressive strength of at least 7.5 MPa for 70.7 mm cubes cured 28 days. It is a mean, not a characteristic value, and the specimen is a 70.7 mm cube — not the 150 mm cube used for concrete. Mortar test results scatter far more than concrete.
Why deduct the water in the sand?
Sand at 2% moisture brings about 30 kg of water per cubic metre; adding the full 280 kg pushes the water-cement ratio over 10% high, costing 15-20% strength and increasing shrinkage. In the rainy season sand can reach 8%. Measure moisture each shift by drying or a rapid meter.
Is more cement always better in mortar?
No. Excess cement increases shrinkage and cracking, mismatches brick movement and costs more. The key property is workability — water retention and consistency — which lime putty or fly ash improve better than extra cement. The code sets a minimum cement content but also discourages over-strong mortar in masonry.