Bored Pile Concrete and Rebar Calculator
Concrete volume, overbreak factor and reinforcement for bored piles.
Inputs
Result
Formula
| Theoretical volume | π r² L with r = d ÷ 2 |
| With overbreak | volume × K |
| Main bars | 0.00617 × d² × count × length |
| Spiral length | π(D − 2c) × (length ÷ pitch) |
| Stirrup mass | 0.00617 × d² × spiral length |
| Steel ratio | steel ÷ actual volume |
Φ800, 20 m long, 20 piles, 1.15 overbreak, 12Φ20 main bars and Φ8 spiral at 200 mm: 10.053 m³ per pile theoretical, 11.561 m³ actual, 231.22 m³ in total, 679.2 kg of steel per pile at 58.8 kg/m³.
FAQ
Why can't the overbreak factor be 1.0?
Because drilling always over-excavates: bit wear, uneven walls and local collapse in sand all make the hole bigger than design, so more concrete goes in than theory allows. Ordering at 1.0 leaves every pile half a cube short, the last one waits for the next truck, and a stopped pour risks a discontinuity. Settlement also measures against the overbreak factor.
What steel ratio is reasonable for a bored pile?
Friction piles usually run 50-80 kg/m³, end-bearing 60-100, and piles taking lateral load or uplift can exceed 120. Below 40 suggests under-reinforcement and needs a crack and bending check; above 150 is usually uneconomic and a precast or steel pile may be the better answer. Steel ratio is a core comparison between pile options.
How does underwater concreting differ?
Underwater work needs the tremie method with a highly workable mix — 180-220 mm slump, aggregate no larger than 40 mm and no more than a quarter of the clear bar spacing, plus a retarder to keep the pour continuous. In a dry hole the slump can drop to 100-140 mm and cement content falls. The wrong mix blocks the pipe, segregates or traps mud in the shaft.
Related calculators
Results are estimating aids only and are not a design basis. Construction and final accounts must follow the drawings, the applicable standards and an approved method statement. Anything affecting structural safety, shoring or falsework must be checked by a suitably qualified engineer.