Concrete Mix Design Calculator

Work out cement, sand, gravel and water per cubic metre from the target grade and water-cement ratio.

Inputs

Strength surplus factor 1.16 for class 32.5, 1.00 for 42.5 and above
mm
30-90 for direct placement, 120-180 for pumping
%
Usually 38-45% for crushed stone pumped concrete

Result

Formula

Target mean strengthfcu,0 = fcu,k + 1.645σ (σ = 5.0 MPa)
Effective cement strengthfce = γc × cement class
Water-cement ratioW/C = 0.53fce ÷ (fcu,0 + 0.53×0.20×fce)
Cement contentmc = mw ÷ (W/C)
Total aggregatems + mg = 2400 − mw − mc
Sandms = (ms+mg) × sand ratio
C30 with 42.5 class cement, 31.5 mm aggregate, 90 mm slump and 38% sand: W/C 0.527, water 199 kg, cement 377 kg, sand 693 kg, gravel 1131 kg — a ratio of 1 : 1.84 : 3.00.

Reference mixes by grade (per m³, medium sand, 31.5 mm aggregate)

GradeW/CCement (kg)Sand (kg)Gravel (kg)Water (kg)
C200.622907501150180
C250.573207151155182
C300.533776931131199
C350.484006801125192
C400.444406651118194

FAQ

How do water-cement ratio and slump relate?
Water-cement ratio governs strength; slump governs workability, and the two pull against each other. For a given grade, a wetter mix either means more water (lower strength) or a superplasticiser (same strength, higher cost). Adding water on site is the worst trade: you save a few yuan of admixture and lose a whole strength grade.
Why is my cement figure higher than the ready-mix supplier's?
Suppliers substitute fly ash, slag and admixtures, cutting cement by 15-30% while keeping total binder constant. This calculator assumes pure cement. With 20% fly ash, multiply cement by 0.8 and add fly ash at about 0.25 times the cement mass to hold the binder content.
What sand ratio should I use?
Sand ratio trades workability against strength: too high loses strength, too low segregates and blocks the pump. Typical ranges for crushed stone: 33-38% at 30-70 mm slump, 38-43% at 70-120 mm, 40-45% for pumped concrete at 120-180 mm. Use the low end for fine sand and the high end for coarse sand; manufactured sand runs 2-3 points higher than natural sand.

Related calculators

Results are estimating aids only and are not a design basis. Construction and final accounts must follow the drawings, the applicable standards and an approved method statement. Anything affecting structural safety, shoring or falsework must be checked by a suitably qualified engineer.